Agenda 2nd Oct 2013 (Minutes in this pen)
1. Review actions:
No.
|
Action
|
Owner
|
Target Date
|
Comments
|
Status
|
33
|
Set up meeting to plan how to get a more complete xxx
|
Jared/Richard
|
12th Sept
|
Richard to speak with George about this
|
In Progress
|
36 |
Arrange Dev meeting to agree top priority items from development xxx |
Marie |
25th Sept |
2 meetings held |
Closed |
37 |
Add migration and nterop to product backlog |
Richard |
25th Sept |
Need to clarify and agree use cases for this. |
Closed |
40 |
Investigate what other components are contributing to self-host performance issues |
Burak |
2nd Oct |
No significant progress to report. |
In Progress |
41 |
Reword xxx " plan item so we do not mislead people, should instead be xxx |
Richard |
2nd Oct |
|
Closed |
42 |
Agree how xxx plan items will be brought to xxx |
Marie/Martin |
2nd Oct |
Agreed that they will follow same approach |
Closed |
43 |
Review performance items in backlog, verify priorities |
George/Devang |
2nd Oct |
George has set up half hour for Devang
|
In Progress |
2. Status update on self-host issues (Recurring item) -
-
Update on what is being tracked
-
What overall progress is being made?
-
Progress on 77942?
|